Monday, July 28, 2008

Con Ed update

Con Edison sent out its weekly e-mail blast about construction in the area on Saturday morning. The work schedule on its Web site right now looks old, so here’s the info for this week and the projection for next week:

Weekly Update
Starting July 27 through Aug. 3:

Work schedule:
Monday to Friday, from 7 a.m. to 3:30 p.m.
• West 225th Street, between Broadway and Kingsbridge Plaza (Pipe installation and restoration)
• Kingsbridge Plaza ramp (Excavation and pipe installation)
• West 230th Street, between Tibbett and Riverdale avenues (Excavation_

In the next two weeks, the utility company said it expects to work in the following areas:
1. Henry Hudson Service Road, between West 239th and 246th streets (Excavation and pipe installation)
2. Riverdale Avenue, from West 257th Street south to West 246th Street (Excavation and pipe installation)
3. Riverdale Avenue, between West 232nd Street and the Henry Hudson Parkway service road (Final restoration)

All schedules, the utility company notes, are subject to change.
For more information, questions and concerns, call 800-799-1083 or e-mail M29project@coned.com.