Friday, August 15, 2008

Con Ed update

Con Edison sent out its weekly e-mail blast about construction in the area yesterday.
What to expect from Sunday, Aug. 17 to Saturday, Aug. 23:

Work schedule:
Monday to Friday, from 7 a.m. to 3:30 p.m.
• West 225th Street and Kingsbridge Plaza Ramp intersection. (Restoration)
• Riverdale Avenue and West 230th Street intersection. (Restoration)

In the next two weeks, the utility company said it expects to work in the following areas:
1. On the Henry Hudson Parkway service road between Manhattan College Parkway and West 246th Street. (Restoration)
2. On Riverdale Avenue, between West 252nd and West 256th streets. (Excavation, pipe installation and restoration)
3. On Riverdale Avenue, between West 230th Street and the Henry Hudson Parkway. (Milling and paving)
4. On the Henry Hudson Parkway, between West 246th and West 252nd streets. (Excavation and pipe installation)

All schedules, the utility company notes, are subject to change.
For more information, questions and concerns, call 800-799-1083 or e-mail M29project@coned.com.